Client: Mr. & Mrs. Diano
Project Code: P25009
Status: On-track
Project Type:
2-Storey Residential House
Location:
Arden Botanical Estates, Trece Martirez City, Cavite
Current Phase:
PLANNING

Updates (Weekly)
Recent
-
Completed ground floor slab casting and curing
-
Delivered and checked rebar and formworks for 2nd floor
-
Coordinated with estate admin on construction access and guidelines
Updates
Next Steps
-
Erect columns and beams for 2nd floor
-
Begin roofing and truss fabrication
-
Schedule on-site walkthrough with you for milestone review
Key Plans & Documents
Weekly Site Photo Archive

Project Timeline Overview
Start:
January 01, 2025
End:
October 01, 2025
Week:
X / Total X
Timeline Status:
(On track, Slightly behind, Ahead)